Chennai Port–Maduravoyal Expressway

Chennai Port – Madhuravoyal Elevated Expressway
Route information
Maintained by National Highways Authority of India
Length: 19 km (12 mi)
Existed: November 2009 – present
History: Completion scheduled for 2013
Major junctions
From: Chennai Port
To: Maduravoyal
Location
Major cities: Nungambakkam
Highway system

The Chennai Port – Maduravoyal Expressway is an 19 kilometres (12 mi) elevated expressway under construction in the city of Chennai, India. The corridor begins at Chennai Port Gate no. 10 and travels along the bank of the Cooum River till it reaches Koyambedu and along the median of NH4 thereon till it reaches Maduravoyal.

History

An 18.3-kilometre (11.4 mi) long, 20-metre (66 ft) wide elevated road project connecting the port with Maduravoyal is under construction at a cost of 16,550 million. Upon completion, this will be the country's longest four-way elevated expressway. The project was sanctioned in June 2007 when the Tamil Nadu Government gave its 'in principle' approval to the National Highway Authority of India (NHAI) for the elevated expressway. The project cost then was put at 14,680 million. In January 2009, the Prime Minister, Dr. Manmohan Singh, laid the foundation stone for the project but the project was put on hold for want of environment clearance.[1] The project has got the environment clearance in February 2011, and during the same month, the port handed over a cheque for 500 million to the NHAI as part of its contribution to the project. The expressway starts from Gate No. 10 of the Chennai Port near the War Memorial and ends before Maduravoyal Interchange. It would run along the banks of the Cooum up to Koyambedu and would end along the Cooum near the Koyambedu grade separator. From there for a distance of three km up to Maduravoyal the elevated expressway would come up on Poonamallee High Road. There would be a total of four entry and exit ramps as part of the project. While the entry ramps would come up on Sivananda Salai and College Road, the exit points would be provided on Spurtank Road and Kamaraj Salai. The work at the Maduravoyal end began in December 2010. The project is being implemented on a build, own and transfer mode. Of the total project cost of 16,550 million, 3,100 million has been set aside for land acquisition and rehabilitation and resettlement of nearly 7,400 people living along the project area. About 1,300 people have been rehabilitated at Okkiam Thoraipakkam. Of 30 hectares to be acquired for the project, only 2 hectares belong to private owners. The project was initially expected to be completed by end of 2013.[2] However, the project has been put on hold.[3][4]

Project Details

This corridor is implemented under Phase-VII[5] of National Highways Development Project by NHAI. The Feasibility study cum DPR was done by Wilbur Smith Associates.[6] This expressway forms a part of the circular corridor 2 of the High Speed Circular Corridors.

Alignment

Interchanges

Main article: Koyambedu Junction

Entry Ramps

Exit Ramps

Project status

7 March 2008:

Jan 2009:

June 2009:

July 2010:

September 2010:

April 2012:

February 2014:

Gallery

References

  1. "Vasan urges speedy execution of Chennai port-Maduravayol expressway". Business Line. Chennai: The Hindu. 27 February 2011. Retrieved 14 Nov 2011.
  2. Lakshmi, K. (5 May 2011). "Preliminary work on elevated expressway along the Cooum begins". The Hindu. Chennai: The Hindu. Retrieved 15 Nov 2011.
  3. Ramakrishnan, Deepa H. (7 November 2012). "Under one govt it's go, under another it's stop". The Hindu. Chennai: The Hindu. Retrieved 7 Nov 2012.
  4. Ramakrishnan, Deepa H.; N. Anand (7 November 2012). "PM's adviser to meet CM for talks on pending projects". The Hindu. Chennai: The Hindu. Retrieved 7 Nov 2012.
  5. .Completed Stretches on Golden Quadrilateral. NHAI (2013-10-31). Retrieved on 2013-12-06.
  6. "Archived copy". Archived from the original on 27 July 2011. Retrieved 2008-12-20.
  7. Tamil Nadu / Chennai News : Elevated expressway to have toll plazas. The Hindu (2009-01-28). Retrieved on 2013-12-06.
  8. .Completed Stretches on Golden Quadrilateral. NHAI (2013-10-31). Retrieved on 2013-12-06.
  9. Tamil Nadu / Chennai News : Elevated expressway work to begin in November. The Hindu (2009-06-18). Retrieved on 2013-12-06.
  10. Nod for expressway. The Hindu (2010-07-26). Retrieved on 2013-12-06.
  11. Ramakrishnan, Deepa H. (7 November 2012). "Under one govt it's go, under another it's stop". The Hindu. Chennai: The Hindu. Retrieved 7 Nov 2012.
  12. Ramakrishnan, Deepa H.; N. Anand (7 November 2012). "PM's adviser to meet CM for talks on pending projects". The Hindu. Chennai: The Hindu. Retrieved 7 Nov 2012.
  13. "Start work on port expressway project, court tells Tamil Nadu". The Hindu Business Line. Chennai: The Hindu Business Line. 20 February 2014. Retrieved 20 February 2014. |first1= missing |last1= in Authors list (help)
This article is issued from Wikipedia - version of the 11/21/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.