Western Harbour Crossing

Western Harbour Crossing
西區海底隧道

Western Harbour Crossing tunnel entrance and exit at West Kowloon side.
Overview
Coordinates Coordinates: 22°18′5″N 114°9′24″E / 22.30139°N 114.15667°E / 22.30139; 114.15667
Status completed
Route part of Route 3
Start West Kowloon
End Sai Ying Pun
Operation
Constructed August 1993 to April 1997
Owner Western Harbour Tunnel Company
Operator Western Harbour Tunnel Company
Traffic automotive
Character immersed tube
Toll yes
Technical
Length 1975 m
Number of lanes 6 lanes (3-lane, 2-way)
Operating speed 80 km/h
Western Harbour Crossing
Traditional Chinese 西區海底隧道
Simplified Chinese 西区海底隧道

The Western Harbour Crossing (abbreviation WHC, 西隧) is a dual 3-lane immersed tube tunnel in Hong Kong. It is the third road tunnel to cross Victoria Harbour, linking the newly reclaimed land in Yau Ma Tei on Kowloon West with Sai Ying Pun on Hong Kong Island. It was constructed by the Western Harbour Tunnel Company Limited (WHTCL) on a 30-year franchise (1993–2023) build-operate-transfer (BOT) model proposed by the Government.

Western Harbour Crossing (WHC) is the first three-lane road tunnel in Asia to be constructed using submerged pipe, and is the newest of the three Victoria Harbour road tunnels.[1] It is part of the Airport Core Programme which was a comprehensive set of infrastructure projects associated with the airport at Chek Lap Kok. The tunnel carries on the Route 3 designation from the West Kowloon Highway, and connects to Route 4 on Hong Kong Island.

The tunnel project

Background

By the early 1980s, the Cross-Harbour Tunnel (CHT) was already stretched beyond its designed capacity of 80,000 vehicle-trips daily, with in excess of 120,000. Furthermore, on the basis of population growth projected from 5.125m in 1981 to 6.34m in 2001, the Second Comprehensive Transport Study (CTS-2) in the late 1980s forecast an explosion in the number of cross-harbour trips individual person trips would increase by 86% from 1.4m to 2.6m, and goods vehicle trips by 129% from 34,000 to 78,000 by 2001.[2]

Also, with the development of the Hong Kong International Airport, it was to be an important component of the strategic Airport Core Programme linking it to the Kwai Tsing Container Terminals and Hong Kong Island.[2] There are 10 km of associated roads (40 km of lanes) and 17 bridges.[1]

The Government announced in 1990 that the tunnel project would be financed as a private venture, with bidding initially scheduled to be called in April 1991.[3] As the project was to span the change in sovereignty of Hong Kong, the support of both the British and Chinese was necessary.[3] In September 1991, the British and Chinese governments signed the Memorandum of Understanding committing their firm support for building the new airport at Chek Lap Kok and its connecting infrastructure.[2] Since mid-1991, private sector companies interested in the project started looking for partners to form consortia. The formal tendering exercise was launched in March 1992 and ended in early July 1992.[3]

In early 1992, two consortia appeared to be vying for the contract. However, one week before the closing date for tenders, Cross Harbour Tunnel Company and CITIC decided to merge their bids. Cross Harbour Tunnel Company, with Wharf Holdings as its major shareholder, dissolved its own consortium in favour of joining with CITIC group; the contractors of the CHT team were dropped.[4] At the close of the tender, the Government was disappointed that there was only one bidder. Upon this news, two new consortia of construction companies proposed to build the project for the Government if the Government decided to pull the tender and run the project itself.[4]

In 1993, the Western Harbour Crossing Ordinance (Cap. 436) was enacted to govern the construction and operation of tunnel. Having decided to rely on the private sector, the government opted for a build–operate–transfer (BOT) model, for 30 years.[2] Tenders for the project were invited, and was won by the Western Harbour Tunnel Company (WHTCL). The franchise was awarded for 30 years, ending August 2023. The Western Harbour Crossing Bill was also passed to award the franchise to the Western Harbour Tunnel Company to build and operate WHC.[2]

WHTCL's single largest shareholder is The Cross-Harbour (Holdings) Limited 港通控股有限公司 SEHK: 0032, which has a 50% stake. Its other shareholders are CITIC Limited 中國中信股份有限公司 SEHK: 0267 and Kerry Properties Limited 嘉里建設有限公司 SEHK: 0683 which hold 35% and 15% effective interests in WHTCL respectively through a joint venture company.

Construction

The project team consisted of John Mundy (project manager), John Porter of Nishimatsu (project director), Kazutoshi Torakai of Kumagai Gumi (technical director), K.C. Tsui (JV construction manager for the mechanical and electrical works), Sandy Hone (JV deputy project manager and construction manager for the civil works), Knud Poulsen (engineering manager), Alex Peling (commercial manager), Robert Lloyd, Eric Granville and Don Ramanaynke (the Government’s Highways Department Western Harbour Link Office engineers).[4] The project cost was HK$7.5bn, funded privately. The project was completed in 1997.[1]

The pipe itself is 2 km long.[1]

Tolls and congestion issues

The initial toll for private cars projected by the consortium was $30. The franchisee traffic forecast in January 1997 made before the tunnel opened was between 50,000 and 70,000 vehicle trips daily during the first year of operation. The actual number of daily trips did not exceed 47,000, and averaged at 20,000.[3]

Toll adjustment mechanism

The Government and the consortium agreed on the toll and its future adjustment where the starting toll for private cars was proposed to be at HK$30. The agreed automatic adjustment mechanism would allow the franchisee to maintain the target rate of return of between 15% and 18.5%. The operator could also increase the tunnel toll by HK$10 whenever its IRR fell below 15%.[4]

Legislators, principally from the pan-democrat camp but including the Liberal Party, criticised the mechanism as being too generous in favour of the franchisee and were unwilling to approve the deal. The government feared that revision at LegCo would adversely impact project viability and force re-opening of negotiations with the consortium. Underlying that were fears the consortium and its banks may withdraw from the project, so wanted the bill voted through as a package.[4]

One week before the final LegCo vote on the deal, in response to legislators' fears, the Liberal Party proposed an amendment that both the Government and the consortium found to be an acceptable compromise: to preserve the HK$30 opening toll, but the return on investment would be capped at 16.5% (instead of 18.5%) for the first three years after the tunnel opened; amounts above that would be transferred the toll stability fund to reduce the need for future toll rises. On 21 July 1993, the legislative council approved by 35 to 19 the amendment proposed by the Liberal Party.[4]

Any changes in tolls must be gazetted. The toll adjustment mechanism allows the franchisee to apply for an increase its tolls on six specified dates during the franchise period depending on revenues achieved. Toll increases and revenue appropriation according to following scenarii were envisaged:[3]

  1. if the actual net revenue generated falls below the upper net revenue projection, the operator may apply for an increase in tolls;
  2. if the net revenue exceeds the upper estimated net revenue but is less than the maximum estimated net revenue, the Company would be entitled to the upper estimated net revenue plus half of the excess and the balance, and the remaining half of the excess is transferred to a 'toll stability fund';
  3. if the actual net revenue is greater than the maximum estimated net revenue, the Company is entitled to the upper estimated net revenue plus half of the excess between upper estimated net revenue and maximum estimated net revenue; the surplus is transferred to the Toll Stability Fund;
  4. If traffic levels and revenue fall below projections, the operator is permitted to bring forward the date of a toll increase according to the mechanism rules. However, the right to increase tolls will be deferred if the revenue received is above the forecast, and a rate of return is over the range specified.[3]

Evolution of tolls

  starting date 1997 2000 2003 2004 2008 2010 2013 2015 2016
Category Vehicle type 30 Apr 3 Dec 16 Feb 4 Jul 6 Jan 1 Aug 1 Jan 22 Feb 31 Jul
                      (Gazetted)
1 Motorcycles, motor tricycles 15 20 20 22 22 23 25 25 25 120
2 Private cars 30 35 37 40 45 50 55 60 60 210
2 Taxis 30 35 35 35 40 45 50 55 55 210
3 Public and private light buses 40 45 47 50 55 60 65 70 70 250
4* Light goods vehicles 45 50 50 55 55 60 65 70 70 300
5* Medium goods vehicles 65 70 70 80 80 85 90 95 95 455
6* Heavy goods vehicles 95 100 100 110 110 115 120 125 125 635
7 Public and private single-decked buses 40 50 60 70 80 90 100 110 110 250
8 Public and private double-decked buses 55 70 85 100 115 128 140 155 155 370
*Each additional axle in excess of 2: $30
source:historic WHC published data

Congestion

  total volume av. daily share
year (million trips) (thousand trips) (%)
1997 5.50 22.35 9.78
1998 12.08 33.10 14.77
1999 14.31 39.21 17.37
2000 15.66 42.80 18.18
2001 14.49 39.70 16.91
2002 14.61 40.04 17.15
2003 13.60 37.26 16.32
2004 14.34 39.30 16.72
2005 15.03 41.19 18.07
2006 16.20 44.37 19.36
2007 17.82 48.82 20.67
2008 17.47 47.74 20.59
2009 17.60 48.22 20.17
2010 19.56 53.58 22.20
2011 20.79 56.95 23.00
2012 22.10 60.55 24.20
2013 22.60 61.92 24.70
2014 23.00 63.01 25.10
source:Transportation Dept., Hong Kong[5]

Due to severe congestion experienced at the Cross Harbour Tunnel and the feeder roads to the WHC, there have been calls for lower tolls at the Western Harbour Crossing by letting the Government of Hong Kong buy back the tunnel from the current owners of the tunnel, WHTCL, so that it can control tolls and ease traffic congestion in the Cross Harbour Tunnel area. To that end, lawmakers passed a non-binding motion in 2008 for the HK Government to address the situation.[6] However the consultant hired by the Government to find a solution to the traffic problem did not suggest the Western Harbour Crossing have lower tolls. The consultants said that lowering tolls would result in a very high increase in traffic volume, with severe congestion on the exit to Route 4 (Hong Kong) during rush hour. This solution would only be possible when the construction of the Central-Wan Chai Bypass is completed.[7]

Transport

Bus routes which use the crossing:

See also

References

Notes

  1. 1 2 3 4 Omega pp.7-11
  2. 1 2 3 4 5 Omega pp.12-15
  3. 1 2 3 4 5 6 Omega pp.39-45
  4. 1 2 3 4 5 6 Omega pp.28-38
  5. "The Annual Traffic Census 2011". Transportation Department, Hong Kong (2012).
  6. Lau, Nickkita (20 November 2008). "Drive for tunnels shake-up wins Legco vote". The Standard
  7. "Consultancy Study on Rationalising the Utilisation of Road Harbour Crossings (RHCs)". Wilbur Smith Associates Limited, November 2010
Wikimedia Commons has media related to Western Harbour Crossing.
Preceded by
Southern Terminus
Hong Kong Route 3

Western Harbour Crossing
Succeeded by
West Kowloon Highway
This article is issued from Wikipedia - version of the 11/22/2016. The text is available under the Creative Commons Attribution/Share Alike but additional terms may apply for the media files.