Greifswald Nuclear Power Plant

"KGR" redirects here. For Kjøbenhavns Grundejeres Renholdningsselskab, see Renholdningsselskabet af 1898.
Greifswald Nuclear Power Plant

Several of the units of the Greifswald NPP
Location of Greifswald Nuclear Power Plant in Germany
Country Germany, previously East Germany
Location Greifswald
Coordinates 54°8′26.11″N 13°39′51.92″E / 54.1405861°N 13.6644222°E / 54.1405861; 13.6644222Coordinates: 54°8′26.11″N 13°39′51.92″E / 54.1405861°N 13.6644222°E / 54.1405861; 13.6644222
Status Decommissioned
Construction began 1967
Commission date 12 July 1974
Decommission date 22 July 1990
Operator(s) Energiewerke Nord
Nuclear power station
Reactor type VVER
Reactor supplier Atomenergoexport
Škoda
Power generation
Make and model Škoda
Electrosila
Units decommissioned 5 x 440 MW
Average generation 10,678 GWh

Greifswald nuclear power station (German: Kernkraftwerk Greifswald, KKW Greifswald), also known as Lubmin nuclear power station, was the largest nuclear power station in East Germany before closure shortly after the German reunification. The plants were of the VVER-440/V-230 type, which was the second generation of Soviet-designed plants. The plant is in Lubmin near Greifswald, in the state of Mecklenburg-Vorpommern.

Closure

In late 1989, nuclear regulatory bodies of countries operating VVER plants found the need to fit many new safety systems, which were stated to have been necessary in almost all areas.[1] All East German reactors were closed soon after reunification, with restarting conditional on compliance with the stricter West Germany safety standards.

Convinced that upgrading to the new safety standards was not economically feasible, the new unified German government decided in early 1991 to decommission the four active units, close unit 5, which was under test at the time, and halt construction of the rest of the units there plus two VVER-1000s at the Stendal Nuclear Power Plant.[2]

The district heating supplied by the plant was replaced by oil imports and in 1995 by a new natural gas plant. Decommissioning of units 1 through 5 began in 1995, making Greifswald one of the first nuclear power stations in Germany to go through the process. The plant came into focus again in 1996 when it was decided to move 235 unspent fuel assemblies to the Hungarian Paks Nuclear Power Plant, which is of the same design.

At its peak, the plant employed around 10,000 full-time workers; around 1,000 are working on decommissioning and other activities at the site.

Incidents

Greifswald control room in 1990

Reactor summary

Unit Type Net Power Total Power Start of
construction
Finish
construction
Commercial
operation
Shut down
Greifswald - 1 (KGR 1) WWER-440/230 408 MW 440 MW 1 March 1970 17 December 1973 12 July 1974 14 February 1990
Greifswald - 2 (KGR 2) WWER-440/230 408 MW 440 MW 1 March 1970 23 December 1974 16 April 1975 14 February 1990
Greifswald - 3 (KGR 3) WWER-440/230 408 MW 440 MW 1 April 1972 24 October 1977 1 May 1978 28 February 1990
Greifswald - 4 (KGR 4) WWER-440/230 408 MW 440 MW 1 April 1972 3 September 1979 1 November 1979 22 July 1990
Greifswald - 5 (KGR 5) WWER-440/213 408 MW 440 MW 1 December 1976 24 April 1989 1 November 1989 24 November 1989
Greifswald - 6 (KGR 6) WWER-440/213 408 MW 440 MW Finished, never operated - -
Greifswald - 7 (KGR 7) WWER-440/213 408 MW 440 MW Canceled - -
Greifswald - 8 (KGR 8) WWER-440/213 408 MW 440 MW Canceled - -

See also

Nuclear plants built in the former East Germany

References